Ensign Drilling SW Rig # 753 is reported Assigned with projected spud date 5/1, 4/25/14.

Views: 1808

Replies to This Discussion

Ensign Drilling SW Rig # 753 is reported Assigned with projected spud date 5/6, 5/2/14

Excerpt from GDP presentation, May 6:

  • The Company is currently drilling its SLC, Inc. 81H-1 (66.7% WI) well in West Feliciana Parish, Louisiana and will commence drilling operations on its Bates 25-24H #1 (97.6% WI) and Denkmann 33-28H #2 (75% WI) wells in Amite County, Mississippi in the coming days.

Ensign Drilling SW Rig # 753 is continuing to report Assigned, projected spud date 5/11/14.

Ensign Drilling SW Rig # 753 spud 5/12, reports 5 Days Drilling @ 3350', 5/16/14.

Ensign Drilling SW Rig # 753 reports 12 Days Drilling Ahead @ 10107', 5/23.

Ensign Drilling SW Rig # 753 reports 19 Days Drilling Ahead @ 10980', 5/30.

Ensign Drilling SW Rig # 753 reports 26 Days Drilling Ahead @ 11,864', 6/6..

Ensign Drilling SW Rig # 753 reports 33 Days Drilling Ahead @ 14694'', 6/13.

Ensign Drilling SW Rig # 753 reports 40 Days Drilling Ahead @ 15205', 6/20.

Ensign Drilling SW Rig # 753 reports 47 Days Drilling Ahead @ 16213', 6/20.

Ensign Drilling SW Rig # 753 reports 54 Days Circulate, 7/3.  Rig assigned to the Kent 41H, projected spud date 7/11.

Skip, 54 days seems like a long time, is circulating good or bad, what does this mean? How long does it circulate after drilling is done? Thanks.