Nabors Drilling Rig 624 reports 8/1 Assigned, Projected Spud Date 8/9.

Views: 1493

Replies to This Discussion

Cool.....Glad to finally see this after being permitted for over a year and then having the unit change.  Thank you Mr. Skip!!

You're welcome.  Good luck.

Nabors Drilling Rig 624 reports 8/8 Assigned, Projected Spud Date 8/13.

Skip:

As always, thanks for all the information, I sure appreciate it.  I don't suppose there was an update about this well mentioned?  For some reason this(these) wells in this unit keep getting put off and put off. 

No mention this week for the 8H #1.  The list of permitted MS TMS wells is long and some for GDP and ECA are about to begin expiring.  That does not necessarily indicate they they won't be drilled as it is a simple matter to get a new permit.  It does indicate that drilling schedules are constantly in flux and subject to change.

Thanks Skip, sure appreciate it. 

Nabors Drilling Rig 624 reports 8/22 Assigned, Projected Spud Date 8/28.

Nabors Drilling Rig 624 reports 8/29 Assigned, No projected Spud Date reported.

Nabors Drilling Rig 624 reports Moving On, 9/5.

Nabors Drilling Rig 624 reports Rigging Up on the 8H #1, Proj. Spud 9/14, 9/12.

This rig is assigned to drill both the 8H #1 & #2.  I'm going to see how it goes tracking both wells in this one discussion thread as the rig moves from one to the other.

Nabors Drilling Rig 624 reports Assigned to the 8H #2, Proj. Spud 9/17, 9/12.

Nabors Drilling Rig 624 spud the 8H #2 9/19.

Nabors Drilling Rig 624 spud the 8H #2 9/19.  8 days Drilling Ahead @3640', 9/26.